JTI GALLAHER PHASE 2 AHU UPGRADE COMPLETE

jti ahu2jti ahu1

 

RJS are pleased to have completed AHU upgrade phase 2 at tobacco processing factory JTI Gallahers.  The project consisted of piping installation of heating, chilled, air, RO water and also supply and extract duct installation along with associated controls to 3No air handling units supplying north and south factories heating and cooling.  3D installation drawings where completed with prefabrication drawings used to fabricate all pipe work off-site to reduce site hot works and installation duration.  RJS’S scope of works where completed before contract end date to the satisfaction of JTI engineering staff.